New Brooklyn bridge in Sheffield – an update
The latest on the Don’s minature Brooklyn bridge
In November 2008 I wrote a post about the proposed New Brooklyn bridge across the river Don in Sheffield. The floods of June 2007 delayed construction but 2009 was expected to see at least the flood wall protection being built, after which the building of the bridge could follow.
I thought I’d get an update on where the project is at. Sheffield industrial museums trust says that construction of the flood wall is due to start imminently now that the tender for it has been awarded.
The changes to the flood wall meant the bridge itself needed to be redesigned and this is now underway. When complete, the cost of the new design will be assessed and the trust will then see if the original sponsors are still on board. They will then work out what the funding gap is and decide if money can be raised to fill it.
There are also complicating factors such as whether the current residents of Brooklyn works will be as supportive as those when the bridge was first proposed, and also whether the proposal to put a water wheel back into the wheel pit to generate electricity for the museum will be compromised by the tower’s affect on water flow.
So although the construction of the bridge is still some way off, the good news is that the project is still moving along.